25. Clark Battery

Information from RCW Form 1 (date): Jun. 30, 1921 - Battery commenced: Aug. 1897 - Battery completed: Nov. 1898 Date of transfer: Jan. 17, 1899 - Material of construction: concrete - Portland or Rosendale cement: Portland - Cost to date of transfer: $71,546.63 - Type of data transmission: none - Trunnion elevation in battery: A1-21.47', A3-21.48', B1-21.50', B3-21.47' - Datum plane: MLLW - Sources of electric current: central or reserve power plant - Max. kw. Required for lights: 4.5 kW - Max. kw. Required for motors: none